Université de Lorraine

Metz, France

Code: CS38

Outside view
© ProPassif
Current building status
© ProPassif
Windows
© ProPassif
Pipe work under the building
© ProPassif

Original situation

1970's non-residential concrete building on the campus in Metz.  The building is used as a training centre for the activities of IUT GMP, Lorraine University. A well and fast renovated building is the aim in this project and would be a big plus.

Renovation approach

External insulation with airtightness treatment on a structure with a complex shape to receive and fix an insulation. Reduction and treatment of thermal bridges in the façade by use of prefabricated elements. The prefabricated elements are currently tested for fire safety and the work on-site is about to begin.

Modernisation proposal

Prefabricated global retrofit to EnerPHit level thanks to a prefabricated wall system. Triple-glaze windows and a comfort ventilation system are already inserted into the wall.

Efficiency improvement

The improvement of an EnerPHit renovated building has an enormous effect in this cold part of the Jura near Geneva: it shows a plus 10x reduction on heating demand!

PHPP verification sheet before retrofit

TFA existing treated floor area (usable floor space)

2730.0 m2

Space heating Heating demand

128.3 kWh/(m2a)

Heating load

55.0  W/m2

Space cooling Cooling & dehum. demand

– kWh/(m2a)

Cooling load

– W/m2

Frequency of overheating (> 25 °C)

2.0 %

Frequency of excessively high humidity (> 12 g/kg)

0.0 %

Airtightness Pressurization test result n50

3.0 /h

Non-renewable Primary Energy (PE) PE demand

144.0 kWh/(m2a)

Generation of renewable energy (in relation to projected building footprint area)

319.0 kWh/(m2a)

PHPP verification sheet after retrofit

TFA existing treated floor area (usable floor space)

2730.0 m2

Space heating Heating demand

23.5 kWh/(m2a)

Heating load

13.0  W/m2

Space cooling Cooling & dehum. demand

– kWh/(m2a)

Cooling load

– W/m2

Frequency of overheating (> 25 °C)

1.0 %

Frequency of excessively high humidity (> 12 g/kg)

0.0 %

Airtightness Pressurization test result n50

1.0 /h

Non-renewable Primary Energy (PE) PE demand

62.0 kWh/(m2a)

Generation of renewable energy (in relation to projected building footprint area)

70.0 kWh/(m2a)

Key facts

Building typology

School | campus | university

Existing treated floor area (usable floor space)

2 730 m2

Building owner

Université de Lorraine

Consulting outphit partner

ProPassif

Project status

Construction phase

Overall budget

2 000 000 €

Contact

Romain Claret
AMO
PLAN 9
Phone: +33 383 31 77 72